Home
current selection: english
auf Deutsch umschalten

Contact persons Bonn

Georg Wandel

Managing director

Phone: +49 2222 8303-34
Fax: +49 2222 8303-26
Mobile: +49 171 6975420
E-mail: g.wandel

Manfred Mevs

Heavy haulage department - Transport permits

Phone: +49 2222 8303-25
Fax: +49 2222 8303-26
Mobile: +49 160 90127500
E-mail: m.mevs

Bernd Segbers

Heavy haulage department - Transport permits

Phone: +49 2222 8303-20
Fax: +49 2222 8303-26
E-mail: b.segbers

Reinhard Treutler   

CAD Engineering

Phone: +49 2222 8303-53
Fax: +49 2222 8303-26
Mobile: +49 160 96310822
E-mail: r.treutler

Artur Schulz 

CAD Engineering

Phone: +49 2222 8303 50
Fax: +49 2222 8303 26
E-mail: a.schultz

Jörg Arens

Transportabteilung

Phone: +49 2222 8303 16
Fax: +49 2222 8303 26
E-mail: j.arens

December 2011

Project Eemshaven

6 preheater of 174 tons to 263 tons

Road transport from Neubeckum to Münster-Hiltrup

Handling of preheaters in Münster-Hiltrup with LR 1750 of RIGA-BAUMANN on barge

[Translate to EN:] Dezember 2012

[Translate to EN:] 2 Transformatoren je 334t.  – 12.500 x 4.000 x 5.020 mm (LxBxH)
 
Transport mit 2 x 20-Achs Plateaufahrzeugen von Mönchengladbach
nach Düsseldorf-Lörick.
 
Umladen der Transformatoren von Plateauanhänger auf SPMT
mittels 770t. Hubgerüst.
 
Aufrollen der Transformatoren auf Ponton mit 14-Achs SPMT.

October 2011

2 transformers 190 ts each 12.400x3.100x4.472 mm

transport from Möchengladbach, Fa. ALSTOM to Düsseldorf-Lörick on 17-axle plateau-trailer

transport duration 1 night from Mönchengladbach to Lörick

transport meassures in total: 284 ts  38.000x5.000x5.800 mm (LxWxH)

in Düsseldorf roll-on ponton-barge

Destination: RWE Power Plant Ensdorf

September 2011

Monströse Kisten auf ihrem Weg nach Passau

Read the article about the transport from Schalchen to the harbour of Passau (German only).

Download

[Translate to EN:] Juli 2011

[Translate to EN:] 2 Öfen je 70t. – 14.950 x 5.724 x 5.724 mm (LxBxH)

Umschlag der Öfen mit 2 x 250t. Autokran im Hafen Köln-Godorf.

Transport vom Hafen Köln-Godorf nach Wesseling mittels 2 x 10 Achs Plateaufahrzeugen.
 
Transportabmessungen je Fahrzeug: 140t. Gesamtgewicht 27.000 x 5.800 x 7.200 mm (LxBxH)

July 2011

From Beckum-Neubeckum to Hamm and transshipment on Ro-Ro barge:

  • 1 Pre-Heater, 238 t, 16.544 x 6.296 x 3.979 mm
  • 1 Pre-Heater, 244 t, 16.237 x 6.285 x 4.212 mm
  • 1 Pre-Heater, 262 t, 16.419 x 6.425 x 4.170 mm

July 2011

2 furnaces each with a weight of 70ts - 14 950 x 5724 x 5724 mm (LxWxH).

Transshipment of the two furnaces in port of Cologne-Godorf with 2 x 250ts Cranes.
For the transport from Cologne-Godorf to Wesseling were used 2 x 10 axle platform vehicles.
 
Transport measurements for each vehicle: 140t. Total weight -  27 000 x 5.800 x 7.200 mm (LxWxH)

[Translate to EN:] Mai 2011

[Translate to EN:] Setzen einer Betonstation am Bahnhof in Königswinter.

Die 45t. schwere Betonstation wurde auf 25m Ausladung über das Bahnhofsgebäude auf das Bahngelände mittels 500t. Autokran ausgerüstet mit 135t. Zusatzballast eingehoben.

[Translate to EN:] Februar 2011

[Translate to EN:] 444t. Transformator 12.700 x 3.900 x 4.750 mm (LxBXH)

Transport mit 40-Achs Kesselbrücke von der Umschlagstelle
Hamm nach Werne in das Kraftwerk der RWE Power AG.
 

  • Abrollen von Ponton mittels 18-Achs SPMT
  • Anheben mit hydraulischen Schwerlastpumpen
  • Anschl. verbolzen in die 2 x 20-Achs Kesselbrückenhälften

 
Transportabmessungen: 773t. Gesamtgewicht - 102m x 4,8m x 4,8m (LxBxH)

June 2011

Loading of 179 t transformer 9500 x 3065 x 4015 mm on transport unit
with our 770 t hydraulic lifting portal.

May 2011

Establish a cement station at the railway station in Königswinter.

The cement station with a weight of 45ts was raised to its position (25m distance) with 500t. mobile crane equipped with a counterweight of 135ts.

February 2011

444t. Transformer 12 700 x 3.900 x 4.750 mm (LxWxH)
Transport with 40-axle vessel bridge from the point of transition
Hamm to Werne, power plant of RWE Power AG.

  • unroll from pontoon with 18-axle SPMT
  • lifting with hydraulic pumps
  • bolting into 2 x 20-axle vessel bridge


Transport dimensions: 773T. Total weight - 102m x 4.8 m x 4.8 m (LxWxH)

January 2011

3 Heat Exchanger and 1 Boiler from Neubeckum to Münster-Hiltrup. At Münster-Hiltrup transshipment on barge.

September 2010

1 Transformer 377t
12500 x 3600 x 4800 mm each

  • 1 Transformer from Mönchengladbach to Düsseldorf. In Düsseldorf roll-on barge and offloading with 770 t lifting portal

July 2010

2 drilling head parts, 58.5 tons each
8.000 x 2.250 x 4.100 mm each

  • From Germany, Erkelenz to Switzerland, power station Linthal

June 2010

2 Behälter 8 m Durchm.,  15 m hoch a 75 t

  • Vom Fundament gehoben und innerhalb der Zuckerfabrik Jülich verfahren
  • Tandemhub mit 500 t Autokran/80 t Autokran, verfahren auf 2 x 6-Achsen SPMT quergekoppelt

June 2010

1 MAN Reaktor 567 t
9.200 x 9.200 x 7.200 mm

  • From Duisburg-Homberg to Moers, Sasol-Werke
  • 2 x 16 Self Propelled Modular Transport axles, paralell-coupled

February 2010

3 transformer 418 tons each
14.200 x 4.410 x 5.300 mm

  • Ex Bad Honnef on 20 axles Self Propelled Modular Transporter to
    Nato ramp and transshipped on barge

December 2009

2 vessels 330 tons each
34.000 x 8.000 x 10.000 mm

  • Transport on water with 600 t floating crane and 600 t spreader beam from Bützfleth to Stader Sand
  • Transshipped onto 40 Self Propelled Modular Transport axles, paralell-coupled to Stade, site DOW Chemicals.
  • Road fortification 150 steel plates
  • Bridge superstructure up to 550 tons
  • Lifting with CC 6800 and LR 1600 cranes

November 2009

1 stator weighing 350 t
12,500 x 4,000 x 4,000 mm

 

  • Transport from Irsching in Bavaria to Kehlheim-Hafen



June 2009

1 transformator weighing 202 t
12,000 x 3,850 x 4,597 mm

  • Pontoon transport from Nijmegen in the Netherlands to Duisburg, Germany
  • Unloading off the pontoon in Duisburg and further transport by road



April 2009

Tunnel drilling machine (TBM = Tunnel Boring Machine)

1 middle shield section, left side weighing 95 t
9,420 x 4,250 x 3,650 mm

1 middle shield section, right side weighing 80 t
8,820 x 4,250 x 3,090 mm

  • Transport from Flieden-Kautz to Bornheim-Hersel

March 2009

4 modules each weighing 150 t

  • Transport by sea from Budapest in Hungary to Rotterdam in the Netherlands
  • In Rotterdam transhipment onto flat top river barge
  • Flat top river barge from Rotterdam to the ramp in Dormagen-Stürzelberg, Germany Water transportation by pontoon
  • Arrival at the Neurath power plant

February 2009

1 generator weighing 367 t
9,800 x 4,521 x 4,552 mm

  • Arrival in Wilhelmshaven by coaster
  • Transhipment onto a 380 t vessel bridge and delivery to the Wilhelmshaven power plant
  • Transfer onto a 16 axle Self Propelled Modular Transporter and arrival at the power plant



February 2009

1 generator weighing 370 t
13,739 x 4,840 x 4,190 mm

  • Using a 700 t lifting frame and loaded onto two longitudinal coupled 14 axles Self Propelled Modular Transporter
  • Unloading at the construction site in the Boxberg power plant

February 2009

1 generator weighing 367 t
9,800 x 4,521 x 4,552 mm

  • Transport from Gelsenkirchen in North Rhine-Westphalia to Dorsten
  • Loading onto a river barge in the harbour of Dorsten using a 750 t crawler crane

January 2009

1 crude argon column weighing 58.2 t
52,100 x 4,800 x 3,850 mm

1 low pressure column weighing 109.8 t
54,400 x 4,950 x 4,350 mm

  • Transport from Tacherting in Bavaria to the harbour of Passau